Corpus Christi Water News
-
City Council Advances $17.8 Million Federal Grant to Replace Water Lines Along Leopard Street and Up River Road
At today’s regularly scheduled City Council meeting, the Council approved a first reading ordinance accepting a $17,830,308 grant from the U.S. Department of War, Office of Local Defense Community Cooperation, to replace aging water infrastructure along the Leopard Street and Up River Road corridor.
-
Mary Rhodes Pipeline Begins Gradual Return to Service
Corpus Christi Water (CCW) and the Lavaca-Navidad River Authority (LNRA) have begun returning the Mary Rhodes Pipeline (MRP) to service following repairs near the O.N. Stevens Water Treatment Plant (ONSWTP) river intake station.
-
Mary Rhodes Pipeline Repairs Progress as Welding Nears Completion
Corpus Christi Water (CCW) continues to make progress on repairs to the Mary Rhodes Pipeline (MRP) near the O.N. Stevens Water Treatment Plant, with welding of the new pipe section expected to be completed today.
-
Corpus Christi Water Making Progress on Mary Rhodes Pipeline Repairs
Corpus Christi Water (CCW) is completing repairs on the Mary Rhodes Pipeline (MRP) after a leak was identified near the O.N. Stevens Water Treatment Plant during a scheduled maintenance period.
-
Corpus Christi Water Investigating Potential Leak on Mary Rhodes Pipeline
Corpus Christi Water (CCW) is investigating a potential pipe leak on the Mary Rhodes Pipeline (MRP) that was identified during the process of returning the pipeline to service after scheduled maintenance.
-
Lavaca-Navidad River Authority & Corpus Christi Water to Perform Scheduled Maintenance and Upgrades to Mary Rhodes Pipeline Pump Stations
On Tuesday, September 29, the Lavaca-Navidad River Authority (LNRA), Corpus Christi Water (CCW), and their contractors will begin scheduled maintenance and upgrades to the Mary Rhodes Pipeline (MRP) pump stations.
-
Mary Rhodes Pipeline Repair Advances to Startup Operations
Today, September 25, startup operations continue for the Mary Rhodes Pipeline (MRP). Filling of the water pipeline continued overnight. The welds connecting the new section of pipe have been inspected, and no issues were identified.
-
Repairs Successful: Water from Mary Rhodes Pipeline Arriving at O.N. Stevens
Repair work is on track to be completed ahead of schedule at the Mary Rhodes Pipeline (MRP) project site, with a portion of the exterior cement work on the repaired pipe joints completed and the excavation partially backfilled.
-
Crews Advance Mary Rhodes Pipeline Repair Toward Testing
Contracted crews have installed a replacement section of the Mary Rhodes Pipeline (MRP) and completed the welded connections this morning.
-
Corpus Christi Water Provides Updates on Mary Rhodes Pipeline Repair and Tap Water Taste and Odor
Corpus Christi Water (CCW) and contracted crews are working around the clock to safely complete the repair and return the Mary Rhodes Pipeline to service.